top of page

Current Work Schedule Info

Work began in October for APS’s contractor, Ferreira UTEC, to access manholes at various locations along the project route to remove and replace the underground line. In some instances, this requires large equipment near the manhole site to remove existing cable, run a robotic device through the pipeline to evaluate its integrity, and install new cable. 

Current Work Schedule:  The current tentative schedule information is provided:

  • Work is currently taking place through March 1 in Coronado Road, between 7th Street and 10th Street for the contractor to splice together the previously installed cables.  This work is accessed from the manholes in Coronado Road, which may be CLOSED to through traffic, between 7th and 10th Street, during work hours to protect the work zone. Local residents and their visitors will be permitted access and detour signage will be in place to direct travelers around the closure area.

  • Scheduled to begin the week of Feb. 26, splicing work will take place in 9th Street, just north of Roosevelt Street. This work is expected to take 1-2 weeks to complete, and 9th Street is expected to remain open during this work, with traffic shifted away from the manholes/work area.

  • Scheduled for the week of March 4, crews will work in 9th Street, just south of Fillmore, to conduct repair work which will require excavation to access the pipeline. This work is being scheduled during ASU Preparatory's Spring Break to accommodate school activities. 9th Street will remain open for travel with traffic shifted away from the work zone. 

  • We will continue to update you as work progresses.

  General Schedule:

  • Oct – Prep manholes & pipe

  • Nov – Remove cable 

  • Oct/Nov - Replace manhole covers

  • Dec – Inspect & clean pipe

  • Jan/Feb – Pull in new cable

  • Mar/Apr – Splice cable segments together

  • Apr – Install mineral oil & pressurize pipe to complete

General Construction Information:  The following general construction information is provided for residential areas in the alignment. In all cases, message boards will be placed in advance of work when there are significant restrictions or road closures. Click on the locations below to view the resident notice. 

Coronado Rd, between 7th & 10th Street: Manholes are located in Coronado Road at approximately where 9th Street would intersect. Coronado will be closed to through traffic at certain times during the project. Local access will be permitted for Coronado residents and their visitors.   (Spanish)

9th St, just north of Roosevelt St:  Manholes are located in 9th Street, just north of Roosevelt St, where 9th St will either be closed to through traffic or limited to southbound travel only at certain times during the project.  Detour signage will be in place to direct travelers around the closure area.  (Spanish)

9th St, south of Fillmore St:  Manholes are located in 9th Street, just south of Fillmore St, where 9th St will be limited to one direction of travel only at certain times during the project.  Detour signage will be in place to direct travelers around the closure area.  (Spanish)

Work will also take place at various times in the following locations.

Restrictions may be in place; however, signage will direct travelers, as needed, to ensure access is maintained: 

  • Country Club Substation at Sheridan/St. Mary's Way between 3rd St & 7th St

  • 9th St, south of McDowell

  • 9th St, between Jefferson St and Washington St

  • Jefferson St Parking Garage

  • Madison St, between Central Ave & 1st St

  • Lincoln Street Substation (on-site)

Thank you for your patience during this important work.